31-May-2002
Image 1 - digging starts
Image 2 - leveling the ground to the shallow depth
Image 3 - layout of pool prior to digging the deep end
Image 4 - 6 hours later (total dig time from virgin soil), da ho be done!
1-June-2002
Image 5 - 5 guys 2 hours erect the walls - a giant tinker toy.
6-June-2002
Image 6 - deck supports in place, walls leveled
9-June-2002
Image 7 - monolithic concrete pour to make the wall supports "permanant"
Image 8 - 5 guys for 8 hours cover the walls below the steel and the bottom with concrete - they earned their pay this day ...
11-June-2002
Image 9 - liner in place and partially filled. All plumbing done. Note the vacuum pumps to keep the liner attached to the walls.
12-June-2002
Image 10 - pool filled and backfill complete
14-June-2002
Image 11 - ground prepped for concrete - forms in place
17-June-2002
Image 12 - concrete poured
19-June-2002
Image13 - fence in place
Panaroma before
Panaorama after